Ultimate vs. Working Loads: Navigating CFA Guidelines for Post-Installed Anchors
An anchor reaching 30kN at failure does not have a 30kN working load . The number recorded when an anchor finally pulls out, breaks or causes the s…
An anchor reaching 30kN at failure does not have a 30kN working load . The number recorded when an anchor finally pulls out, breaks or causes the s…
A request to pull test the anchors to 10kN may sound clear on a construction site, but under BS 8539 it is not enough information to define a tec…
“Can you carry out a pull-out test on these anchors?” is one of the most common requests received on construction projects. The problem is that pul…
Anchor testing is frequently requested late in a construction programme, often when a contractor needs evidence that installed fixings are suitable…
Cut-and-carve projects are placing old concrete structures under loading conditions many buildings were never originally designed to carry. Across Lo…
Structural testing RAMS documents are often treated as basic paperwork uploaded shortly before site mobilisation. On live construction projects, tha…